The provincial government has released a data centre development policy which gives communities a voice in data centre proposals and outlines government's strict criteria for government to use when evaluating data centre proposals in New Brunswick.
No proposed data centre will be approved by government unless the following measures can be demonstrated:
- Ratepayer and electricity system impact: Data centre developments will not be approved unless they provide a net benefit to electricity utilities and their customers and must not compromise system reliability.
- First Nations and community benefits: Meaningful engagement with communities and First Nations will be required throughout the development process. Commitments made with First Nations and communities should be supported by binding agreements.
- Water, environmental and community impact: Data centre developments will not be approved unless they are designed to minimize impacts on air, greenhouse gas emissions, water, land, local infrastructure and the environment, while promoting the responsible use of resources.
- Economic value: Projects must demonstrate the economic benefits they bring to New Brunswick, including new investments, job creation, workforce training, research and innovation, and opportunities for local and First Nations businesses.
- Project viability and alignment: The provincial government will not approve projects unless they can demonstrate they are technically and financially sound, are compatible with provincial economic, environmental and infrastructure objectives, and align with provincial and national priorities, including data sovereignty.
Post-Secondary Education and Training Minister Jean-Claude D'Amours said the policy outlines the criteria a project must meet to move forward while giving government the tools to say no to any project that is not right for New Brunswick.
"We know New Brunswickers have concerns about data centres, and that is why we have set the bar high," said D'Amours. "We will say no to projects that don't meet our requirements, and they won't be allowed to proceed."
The government will pursue any legislative and regulatory changes that are needed to implement the policy.
Recently proposed amendments to the Local Governance Act, if passed, would enable local governments and rural districts to determine if a data centre proposal is right for their community. If they feel it would be beneficial, they can negotiate community benefit agreements with the proponent. A community benefit agreement is a contract where a developer commits to providing amenities, services, in-kind benefits, local hiring commitments and/or funding to a community to offset anticipated impacts from the development.
Ratepayer and electricity system impacts are also key considerations when assessing data centre projects.
"Energy demands are always a significant concern, and ensuring New Brunswickers continue to have access to the reliable electricity they depend on in their daily lives remains a top priority for our government," said Energy Minister René Legacy. "As we evaluate new projects, it is essential that they demonstrate clear, measurable benefits for the people of New Brunswick and align with our priorities."
The government intends to introduce amendments to the Electricity Act that, if passed, would establish a new role for government in reviewing and approving electricity supply arrangements for proposed data centres, with a focus on protecting ratepayers and ensuring benefits for New Brunswickers.
Lastly, the government will amend the Environmental Impact Assessment Regulation under the Clean Environment Act to require large data centre developments to be registered for an environmental impact assessment.
The new policy will apply to all proposed data centre developments in New Brunswick, regardless of their current stage of planning or development. Projects already under consideration will be subject to the same requirements as any new proposals brought forward.